ZCCM-IH’s $2.7bn plan for Zambia’s next decade of copper and power
Zambia’s state mining investor has set out a ten-year strategy to put $2.7bn into mines, exploration, metals trading and 3,022MW of new generation, built on the royalty it already earns at Kansanshi and aimed at the government’s target of 3 million tonnes of copper a year by 2031.
ZCCM Investments Holdings (ZCCM-IH), the state company that holds Zambia’s stakes in many of its copper mines, will put $2.7bn into mining and power generation between 2026 and 2035 under an investment plan unveiled at its Shareholder Day in Lusaka on 16 November, which it expects to lift annual revenue from about $211m to $738m and its market value from around $1.2bn to $7bn.
Of the $2.7bn, chief executive Kakenenwa Muyangwa told Reuters, about $700m will be borrowed and up to $1.7bn could come from partners, though not all of that money has yet been secured, and the heaviest spending, $1.2bn, falls in the growth phase between 2029 and 2031.
Zambia produced about 890,000 tonnes of copper in 2025, and President Hakainde Hichilema’s government wants 3 million tonnes a year by 2031, a more than threefold rise that ZCCM-IH intends to support through expansions at the nine producing mines in which it holds stakes and by raising its share of the Mingomba project, which KoBold Metals is developing for first production in the early 2030s, from 20% to 25%.
The royalty ZCCM-IH already earns at Kansanshi, where a 2023 agreement with First Quantum Minerals gives it 3.1% of the mine’s revenue in place of dividends on its 20% stake, is expected to bring in more than $990m over the decade. Muyangwa said talks on similar terms were under way with the company’s other partners, who include Vedanta and Abu Dhabi’s International Resources Holding, though none has yet been announced. Where a royalty does not suit, ZCCM-IH will look for clearer dividend policies instead.
A new energy holding company is to build a generation portfolio of 3,022MW by 2035, including 312MW of solar under the Presidential Constituency Energy Initiative and the Ever Great power project, after power shortages during the 2024 drought held back copper production in a country that relies heavily on hydropower. The portfolio would contribute to the government’s target of 10,000MW of generating capacity by 2031, and ZCCM-IH will keep the dividends it already receives from Copperbelt Energy Corporation and Maamba Energy.
Gold and manganese buying centres with traceability systems will open the company’s move into trading, followed by a stockyard and trading in copper and energy, with the aim of handling 20% of Zambia’s formal gold trade and 35% of its manganese trade by 2035 while bringing more than 30,000 artisanal and small-scale miners into the formal market. “We cannot continue to export raw value and import finished value,” said Muyangwa.
Exploration is to receive about $704m, and Muyangwa told Reuters that fresh discovery was essential because many of the mines producing today were developed decades ago. Among seven priority programmes, the Rufunsa gold project is to drill 10,000 metres by the end of 2028, with an initial resource estimate expected between 2029 and 2031, while a nationwide aerial geophysical survey by Xcalibur Smart Mapping, more than 94% complete in September, is due to finish by the end of the year.
“Over the last three years we showed we can deliver,” said Muyangwa, who wants the next decade judged on a single figure. “Our ambition is a US$7 billion company, and we expect to be measured against it.”