The EBRD and Tunisia’s state utility STEG have signed €50 million of financing for a 50MW solar plant with a 10MW/20MWh battery at Béni Mhira in Tataouine, the country’s first utility-scale battery storage, with construction due to start in early 2027 and the plant expected to be operating by summer 2028.

A 10MW/20MWh battery energy storage system beside a 50MW solar plant at Béni Mhira, in the southern governorate of Tataouine, will be Tunisia’s first utility-scale battery storage, financed with €50 million that the European Bank for Reconstruction and Development (EBRD) and the state utility, Société Tunisienne de l’Electricité et du Gaz (STEG), signed in Tunis on 11 November. The financing also covers an MV/HV substation and about 1.2km of high-voltage line.

Of that total, €30 million is an EBRD loan and €20 million a concessional loan from the Clean Technology Fund, both backed by a state guarantee, and Tunisia’s Minister of Economy and Planning, Samir Abdelhafidh, said the financing would be repaid over 18 years with a five-year grace period, according to African Manager, with a €4 million technical assistance grant supporting the project’s preparation.

STEG issued the tender for the project on 5 October, with construction due to start in the first quarter of 2027 and the plant expected to be operating in summer 2028.

Tunisia is aiming for renewables to supply 35% of its electricity by 2030 and 50% by 2035, which would need 4,850MW of operating renewable capacity by 2030 and 8,350MW by 2035, and the agreement takes the EBRD’s cumulative public-sector financing in the country to €940 million across eight projects under implementation.

George Akhalkatsi, appointed head of the EBRD’s Tunisia office in June, said that “solar energy combined with battery storage is currently the most cost-effective energy source worldwide”, while STEG’s Chief Executive, Faisal Trifa, described the project as “demonstrating that the energy transition is built progressively, kilowatt-hour by kilowatt-hour”.